Project Schedule
Week of April 26
1 Pace Plaza West – 4, 5 and 6th Floor Renovation
Construction continues on schedule:
4th Floor
- Door Frame Delivery and installation will occur this week.
- Acoustic spraying of the ceiling between 3:00 p.m.–10:00 p.m.
5th Floor
- Floor layout and construction preparation will occur this week.
- Partition framing and duct installation will commence at the end of the week.
6th Floor
- Frame new roof openings will begin on Tuesday
- Sprinkler and plumbing work underway
- Acoustic spraying of the ceiling between 3:00 p.m.–10:00 p.m.
Roof Top Units Replacements
- Abatement complete.
- Demolition underway.
- Steel dunnage reinforcement.
4th Floor
- Sheetrock Installation